Almost every backyard disaster we get called into is a sequencing problem, not a craftsmanship problem.
1. Demolition and excavation
Everything that is coming out, comes out first — old deck, old patio, dead sod, construction debris left by the builder. Machines need access while there is still room to move.
2. Grade and drainage
Levels, slope and any drainage go in before anything is built on top. This is the stage nobody photographs and the one that decides whether the yard works.
3. Structure
Retaining walls, then patio base and stone, then steps. Heights are tied together — a patio laid before the wall beside it is a patio that will not meet the wall cleanly.
4. Utilities
Low-voltage lighting runs, irrigation lines and gas for a fire feature go in while trenches are open and before sod. Adding them later means cutting into finished work.
5. Planting, sod and finishes
Last, because everything before it involves machines, mud and material stacked on the ground.
If a pool is part of the plan, the shell goes in before the deck, and the deck contractor should be in the conversation before the pool contractor breaks ground.
Read next

Your new-build backyard is compacted clay. Now what?
What the builder actually left you in Maple or Vaughan, and the order to fix it in.
Read
How to phase a landscape project without wasting money
Splitting a build across two seasons works — if you split it along the right line.
Read
Eight questions that separate landscape contractors
None of them are about price, and all of them are answerable in one sentence.
ReadFree estimate
Planning something like this?
Send the address and a photo, or call or text 647-621-8592.