How to phase a landscape project without wasting money

Most people phase by area: patio this year, the rest next year. That is usually the expensive way to do it.

Phase by layer, not by zone

Do all the earth-moving, drainage and structure in year one, across the whole yard. Then do planting, lighting and finishes in year two. Machines come once, spoil leaves once, and nothing gets dug up twice.

What belongs in year one

  • Demolition and disposal
  • Grade and drainage across the property
  • Retaining walls, patio, steps
  • Conduit for lighting and irrigation, even if unused

What can wait

  • Planting beyond a few anchor shrubs
  • Lighting fixtures
  • Outdoor kitchen, pergola, fire feature
  • Sod in areas you can live with as bare ground for a season

Draw the whole plan anyway

Even if only half is being built, the design covers the whole yard. Otherwise year two begins by undoing part of year one.